May 2025

As construction at AYANA Heights continues to move forward with precision and purpose, we are pleased to share the latest site progress for May 2025. Our teams have made meaningful headway across multiple buildings, ensuring every phase is executed with the quality and care synonymous with the AYANA brand.

Building E has now completed 100% of its piling work, with 90% of pile foundation cutting completed. The reinforced concrete tie retaining wall is now also in place, establishing a critical element of the building’s structural integrity.

Building F is advancing steadily, with piling work now over halfway complete at 51%. Pile foundation cutting stands at 40%, marking consistent movement toward structural development.

Building G has completed all piling work, with pile foundation cutting at 35%, a strong indication of ongoing momentum on-site.

Building H mirrors similar progress, with piling work finalized and pile foundation cutting now reaching 64%, bringing this building into the next phase of its structural development.

Meanwhile, Building C has completed 100% of its earthwork excavation. This foundational milestone paves the way for subsequent structural activity to commence without delay.

Every step forward reaffirms our commitment to delivering AYANA Heights as a premium lifestyle investment.

With panoramic sea views, refined tropical architecture, and meticulous attention to engineering standards, each building is shaping into a signature piece of this prestigious hillside development.